CLIENTSolomon WaterSUB CONTRACTORGEL (Main Contractor)DURATIONMay 2023 – August 2023

Project Overview
We supplied new main switchboard and controls from pump station to bore hole to reservoir tank. GEL acted as main contractor for this rehabilitation project, removing and replacing bore pumps and electrical control systems across three bore field sites, restoring reliable water supply infrastructure for the capital.
Delivered by our Guadalcanal Electrics Ltd labour division, this project reflects the standards of safety, quality, and operational continuity that Traverse brings to every assignment — from major infrastructure to fast-turnaround commercial work.