Back to ProjectsCommercial / Electrical

NPF Building — Main Switchboard Upgrade

ClientNPF / PPI IndustriesMain ContractorGEL (Main Contractor)DurationJuly 2019 (5 days)
NPF Building — Main Switchboard Upgrade
Project Overview

GEL designed, fabricated, and installed a new main switchboard (MSB) at the NPF Building, including full disconnection of mains and sub-mains cabling, removal of the old ATS and MSB, installation of the new board, and reconnection and metering.

Delivered by our Guadalcanal Electrics Ltd labour division, this project reflects the standards of safety, quality, and operational continuity that Traverse brings to every assignment — from major infrastructure to fast-turnaround commercial work.

Gallery

Project images

NPF Building — Main Switchboard Upgrade — image 1NPF Building — Main Switchboard Upgrade — image 2NPF Building — Main Switchboard Upgrade — image 3
Start a Project

Have a project like this? Request a quote.